Garage Conversion ADU in Lakewood: What It Takes and What It Costs
A garage conversion ADU in Lakewood typically runs $45,000 – $130,000 and takes about 4 to 6 months from permit submission to final inspection. You’re converting an existing attached garage into a legal, permitted dwelling unit, which means new insulation, drywall, flooring, a bathroom, a kitchenette, upgraded electrical, and a heating and cooling solution. Call (888) 255-8179 and we’ll walk your garage and give you a real number, not a ballpark.
Key takeaways:
- Realistic budget: $45,000 – $130,000, depending on bathroom count, kitchen scope, and how much of the existing slab and framing can stay.
- Typical timeline: 4 – 6 months, with 4 – 8 weeks of that spent in plan check with the City of Lakewood before a single nail is pulled.
- Your garage door opening gets framed and finished, but the driveway still needs to serve as parking or access. We plan that on day one.
- Every conversion we build is covered by our 730-Day Done Right Promise.
How we run a garage conversion, stage by stage

This is not a “we handle everything” pitch. Here is the actual sequence, with the decisions you make and when you make them.
Stage 1: Site assessment and design (2 – 3 weeks)
We start by measuring the garage, checking the slab for cracking or settlement, and confirming ceiling height. Most Lakewood garages sit at 8 feet, which clears habitable space requirements, but we verify rather than assume. You decide the layout here: one bedroom and bath, or an open studio with a kitchenette. This is also when we check whether the existing electrical panel has capacity for a new subpanel and whether the garage shares a wall with the house that will need fire-rated separation.
Stage 2: Permits and plan check (4 – 8 weeks)
Garage conversions are permitted work in Lakewood. Plans go through the City’s plan check, and depending on how the unit is classified, you may also need a setback confirmation and a utility connection review. We handle the submittal and respond to plan check comments, which is where a lot of homeowner-run projects stall. You decide nothing during this stage except whether you want to bundle other work. Most homeowners don’t; they want the unit done.
Stage 3: Demo, framing, and rough-in (3 – 5 weeks)
The garage door gets removed and the opening framed and sheathed. Interior walls go up, then rough plumbing for the bathroom and kitchenette, then electrical rough-in with a new subpanel, then HVAC. This is the messiest stretch. If your garage shares a slab with the house, we often have to cut and patch concrete for drain lines, which is why we plan the bathroom location early. You make one big decision here: how the unit gets heated and cooled. A ductless mini-split is the common choice. Running a duct off the house system is possible but usually costs more and performs worse.
Stage 4: Insulation, drywall, and finishes (4 – 6 weeks)
Spray foam or batt insulation in the walls and ceiling, then drywall, then flooring, then the bathroom tile, kitchenette cabinets, and paint. You pick finishes before this stage starts, not during it. Material lead times for cabinets and fixtures are the single biggest cause of schedule slip, so we lock selections at the end of Stage 3.
Stage 5: Final inspections and punch list (1 – 2 weeks)
Final building, electrical, plumbing, and mechanical inspections, then a walkthrough with you. Anything on the punch list gets fixed before we close the job. That final walkthrough is also when you get the paperwork you’ll want if you ever sell the home: the permits and the signed-off inspection records.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The options you’ll actually choose between
Most of the budget swings come from four or five decisions. Here they are with the honest trade-offs.
- One bath or a bath plus a half-bath: A single full bath keeps the plumbing in one wet wall and saves $8,000 – $15,000. Two bathrooms cost more and add complexity, but they make the unit far easier to rent long term.
- Kitchenette vs. full kitchen: A kitchenette with a sink, small fridge, and two-burner cooktop is the norm for a garage conversion ADU and keeps the layout flexible. A full kitchen with a range and vented hood is possible but pushes electrical, venting, and permit scope up.
- Ductless mini-split vs. through-wall unit: A mini-split costs more up front but runs quietly and handles Lakewood’s hot dry summers and cool marine-layer mornings well. A through-wall unit is cheaper and simpler but louder and less even.
- Luxury vinyl plank vs. tile flooring: LVP is the value choice and handles a slab-on-grade garage floor well. Tile costs more and feels cooler underfoot, which some renters prefer.
- Window replacement: Many Lakewood garages still have original single-pane windows. Upgrading to dual-pane units from brands like CGI or ES Windows tightens the envelope and cuts noise from the driveway. It adds cost but usually pays back in comfort.
- Fire separation and egress: Not optional. A garage conversion needs a fire-rated wall separating it from the house and a code-compliant egress window in the sleeping area. These are code items, not upgrades.
Homeowners often pair this with Cabinets & Countertops in Lakewood when they want the kitchenette to match the main house, and with Backsplash, Tile & Flooring in Lakewood for the bathroom and living area finishes. Doing them together saves a mobilization.
What a Garage Conversion ADU costs in Lakewood, CA

Expect $45,000 – $130,000. The low end is a studio with a kitchenette, one bath, and standard finishes. The high end is a one-bedroom with a full bath, upgraded systems, and premium finishes.
| Line item | Typical range |
|---|---|
| Design and permit handling | $4,000 – $12,000 |
| Demo, framing, and garage opening | $6,000 – $16,000 |
| Electrical with new subpanel | $5,000 – $14,000 |
| Plumbing and bathroom rough-in | $4,000 – $12,000 |
| HVAC (mini-split or equivalent) | $4,000 – $11,000 |
| Insulation, drywall, and paint | $5,000 – $13,000 |
| Bathroom and kitchenette finishes | $9,000 – $28,000 |
| Flooring and windows | $4,000 – $14,000 |
What pushes a job to the high end: adding a second bath, running a full kitchen, discovering slab or framing problems under the old garage floor, and choosing premium finishes. What keeps it low: keeping the bathroom in one wet wall, standard fixtures, and reusing the existing electrical service where capacity allows. Our written estimates are line-item and fixed. The number you see is the number you pay, and we don’t come back asking for more once demo starts. Financing at 0% for 18 months is available, and projects over $10,000 get $1,000 off.
See the difference
Before
After
Before
After
Before
AfterWhat Lakewood homes specifically do to this job
Nearly every home in Lakewood is a 1950s single-story tract house: stucco over wood frame, slab-on-grade, attached garage, roughly 1,100 square feet. That shared DNA matters here. Because the whole block was built to the same plan, a structural fix that works on one garage almost always works on the next, which is why we can move faster on a Lakewood conversion than on a one-off custom build. The flip side is what’s under the slab. The original clay sewer laterals under these homes are failing at scale, so any conversion that adds a bathroom drain connection routinely triggers a lateral replacement that wasn’t in the original scope. We inspect the lateral before we quote so that surprise stays out of your project. ZIPs 90712, 90713, 90714, and 90715 are where we do most of this work, and we’ve learned to budget for it. When the project scope grows beyond a single garage, that’s a conversation for our Home Additions & ADU in Lakewood page, which covers the wider work.
If we haven’t covered your street yet, we work throughout Lakewood and neighboring areas, and our Home Additions & ADU service is the parent of everything on this page.
Serving Lakewood, CA – Our Local Coverage Area
We serve Lakewood and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – Garage Conversion ADU in Lakewood

Four to six months, with 4 – 8 weeks of that in plan check before construction starts. The build phase itself runs 10 – 14 weeks for a standard one-bedroom. Call (888) 255-8179 for a schedule specific to your garage.
Yes. A garage conversion ADU is permitted work and needs building, electrical, plumbing, and mechanical inspections. We pull the permits and handle plan check; you don’t file anything yourself. We’ll walk you through what the City requires for your property.
Partially. The building shell and slab usually stay. What almost always moves is plumbing: a bathroom needs a drain line, and on a slab-on-grade Lakewood home that means cutting concrete unless the garage sits near an existing drain stack. We locate the drain before we quote, so you know whether concrete work is in or out.
$45,000 – $130,000, depending on bathroom count, kitchen scope, and finishes. Most jobs land in the $65,000 – $90,000 range. Call (888) 255-8179 for an exact quote, and remember estimates are free.
Every garage conversion we build is covered by our 730-Day Done Right Promise. If something isn’t done right, we make it right. That’s one of the longest workmanship guarantees in residential construction, and it’s in writing.
Get your free on-site estimate
We’ll come to your garage, measure it, check the slab and the sewer lateral, and give you a written line-item estimate for your garage conversion ADU in Lakewood. Call (888) 255-8179 to schedule. Calls are answered by a live person 24/7, so you won’t hit voicemail. Estimates are free, and we’ll tell you plainly whether your garage is a good candidate before you spend a dollar.